Sierra Madre Gold & Silver – Q2 Operations, Financial, Exploration Update At La Guitarra & Del Toro
The KE Report Sep 7, 2026 21:13
Summary
Daily throughput at La Guitarra climbed 34% to 672 tpd, with a new ball mill set to push capacity to roughly 1,400-1,500 tpd.
Q2 AISC (All-In Sustaining Cost — what it really costs to produce an ounce) jumped to $5,473 from $3,254 on FX, development, and lower-grade ore.
Sierra Madre plans a year of mapping at Del Toro's three past-producing mines and 3,000 tpd mill before any restart decision.
Phase 1 drilling at La Guitarra begins early Q4 with 13 long holes; Del Toro drilling is slated for mid-2027 — roughly 60,000m combined.
Repayment of the First Majestic Silver term loan leaves Sierra Madre with $22.2M cash and $25M working capital and no funded debt.
Key points on First Majestic Silver
- The CEO notes Sierra Madre paid off its $4.5 million First Majestic loan more than a year ahead of a three-year term, at 50% interest, from operating cash flow.
- First Majestic is also referenced as a past operator that developed some of the underground levels Sierra Madre is now reopening at La Guitarra.
Key points on Pan American Silver
- The CEO points out that Del Toro sits next to Pan American Silver's La Colorada mine, describing the area as an 'incredible copper-silver skarn' relevant to Del Toro's exploration upside.
Key points on Sierra Madre Gold and Silver Ltd
- The CEO argues Q2 throughput reached 672 tons per day at La Guitarra (about a 34% jump) and that a larger ball mill, due online by end of September, should push capacity to 1,400-1,500 tons per day.
- All-in sustaining cost rose to $5,473 in Q2 2026 from $3,254 a year earlier, with the CEO attributing roughly 15% to FX, about $10/oz to extra underground development work, and lower-grade development ore blended into the mill feed.
- The company paid off its $4.5 million First Majestic loan more than a year ahead of a three-year term and ended Q2 with about $25 million in cash and no debt on the books.
- At Del Toro, the CEO frames the acquired 3,000 ton-per-day Zacatecas facility as a long-dated growth asset, with 20,000-30,000m of exploration drilling planned for mid-2027 and notable copper skarn and manto potential alongside mid-sulfidation veins.
- A custom drill rig with kilometer-long holes targeting up to 30,000m at La Guitarra is set to begin in early Q4 2026, which the CEO calls a major catalyst for both geological information and a possible market rerating.
Shad Markwitz's takeaways
- Top takeaway As host, Markwitz frames the discussion around the catalysts investors care about: cost trajectory, the throughput ramp, and the upcoming drill programs at La Guitarra and Del Toro.
- He underscores that running development ore through the mill at current metal prices is 'a symptom of higher metals prices' and is not eating into reserves.
Alex Langer's takeaways
- Top takeaway Langer argues Sierra Madre is in a rerating window, pointing to 672 tpd throughput, a larger ball mill bringing capacity to 1,400-1,500 tpd, and expected cost reductions starting in Q4 2026 and continuing into Q1 2027.
- He positions Del Toro as a long-dated exploration asset: the facility is too large and the resource too thin to justify starting small, so the plan is to drill first (mid-2027) before any commissioning decision.
- On costs, he expects AISC to fall as underground development tapers, the company shifts from rental to owned equipment (close to $10 million of mobile fleet bought over the past year), and grade lifts as higher-grade Colosso ore is blended into the mill.
- On macro, Langer says he is constructive on silver and gold over the next couple of years, framing recent dips as healthy within a longer uptrend.
- He flags the upcoming custom drill rig with kilometer-long holes at La Guitarra (starting early Q4 2026) as a near-term catalyst, arguing each hole should intersect multiple veins and meaningfully expand the geological picture.