This Gold Company Is About to 12X Production | Richard Young - i-80 Gold

The Deep Dive Jul 10, 2026

Summary

i-80 Gold's CEO says financing is now locked in, covering the Nevada build-out through 2032.

Gold's central bank buyers now absorb about a quarter of mine supply, the guest says, underpinning his constructive price view.

A three-phase plan targets roughly 50,000 ounces this year rising to more than 600,000 ounces in 2032.

Five feasibility studies and commissioning the refurbished Lone Tree plant are the milestones investors should watch over the next year.

Study timing slipped because one team now runs two underground projects, after drill results cut the need for a third mine.

Key points on Barrick Mining

  • i-80 says Interstate 80, the source of its name, crosses two of Nevada's biggest and most prolific gold trends, the ones Barrick built itself on.
  • i-80's four past-producing operations were acquired from Barrick and Newmont.

Key points on Newmont

  • Newmont is named alongside Barrick as one of the companies that built itself on Nevada's biggest and most prolific gold trends.
  • i-80's four past-producing operations were acquired from Barrick and Newmont.

Key points on i-80 Gold Corp

  • Management's headline plan is a three-phase ramp from roughly 50,000 ounces in 2026 to 200,000 ounces in 2028, about 400,000 ounces in 2030 and over 600,000 ounces in 2032.
  • Young says the company is now fully funded, including the option to swap phases two and three, and that the over-raise was made for that purpose; the call on whether to flip them is expected in the second half of 2026.
  • Phase one targets roughly 200,000 ounces in 2027 by ramping the first underground, constructing the second underground mine Archimedes and refurbishing the Lone Tree plant, with both the mine and the plant described as on budget and on schedule.
  • The funding came from three packages since March 2026: $250 million from a Franco-Nevada royalty, $288 million of senior notes and a $250 million National Bank prepayment facility, of which $150 million is already drawn.
  • Young attributes the slipped technical studies to one team covering two mines plus a deliberate reschedule of a third mine's development rather than weak results, and says drilling at Granite Creek and Archimedes should keep the mill full for at least a decade.

Key points on Franco-Nevada Corp

  • i-80 raised $250 million through a royalty agreement with Franco-Nevada, one of three financing packages completed since March 2026.
  • The royalty steps up from 1.5% to 3% in 2031, which Young frames as modest capital repayments spread over roughly five years.

Key points on Vox Royalty Corp

  • i-80 terminated the offtake arrangement that was in place with the Vox royalty.
  • Young estimates the termination nets an extra $10 to $20 million in cash over the next two years or so, at a cost of about $4.8 million in equity.

Steve Hyland's takeaways

  • Top takeaway The host frames i-80 as a chaotic business with many near-term cash-flowing opportunities while calling Young one of the calmest CEOs he has interviewed.
  • He identifies funding as the one common thread investors were waiting on, says i-80 has now secured it, and closes by asking what management execution over the next 12 months should look like.

Richard Young's takeaways

  • Top takeaway The guest argues gold prices moved too fast, retrenched, and are now behaving as expected, and that central banks flipped from net sellers from 1990 through the GFC to net buyers, stepping up after Russia invaded Ukraine and now taking 25% of mine supply; he expects prices to move up again over the balance of 2026 and into 2027.
  • He says i-80 is fully funded including the option to swap phases two and three and that the capital was over-raised for that reason; he puts Mineral Point at possibly half the company's value and expects to know in the second half of 2026 whether a pro-business US administration allows it to be accelerated.
  • He expects roughly 200,000 ounces in 2027 as the first underground ramps, Archimedes is constructed and the Lone Tree plant is refurbished, describing the mine and the plant as on budget and on schedule.
  • He attributes the delayed technical studies to one team working on two projects and a rescheduling of a third mine's development rather than results, and says drill programs at Granite Creek and Archimedes should fill the mill for at least the next decade.
  • His near-term milestones are publishing five feasibility studies to confirm the value carried in the preliminary assessments, with commissioning of parts of the plan hoped for by around this quarter next year.