Troilus Mining advances basic and detailed engineering with integrated EPCM structure, targeting a construction decision in late 2026.
The company filed its ESIA for the Quebec project, marking a major permitting milestone after five years of comprehensive baseline studies.
Troilus signed an MOU with Boliden for copper-gold concentrate offtake and is actively building out the capital stack for financing.