GoGold Fully Funded: Los Ricos South Construction Starts - Path to 17 Moz

Mining Network Jul 14, 2026

Summary

GoGold holds $284 million in cash against roughly $250 million of updated capex, funding the Los Ricos South silver-gold build in Jalisco debt-free.

The CEO guides to $12-15 AISC (All-In Sustaining Cost — what it really costs to produce an ounce), a margin that holds up if prices fall.

Permits are secured, detailed engineering is 80% complete and the SAG mill is ordered, so the 24-month build could finish early.

Output is slated to rise from about 2 million ounces (Moz) silver-equivalent to 9 Moz, then 15-17 Moz once Los Ricos North is built.

Management calls the district generational: 15 years of planned reserves plus untested old workings and targets such as San Pedro Alco.

Key points on First Majestic Silver

  • The guest uses First Majestic as the scale comparison for GoGold's district plan: at 15-17 Moz silver-equivalent a year, GoGold would produce about half or a little more of First Majestic's output.
  • He cites First Majestic at roughly a $10 billion US market cap with costs including G&A around $30 per ounce of silver, a cost level GoGold does not have today.

Key points on Hecla Mining Company

  • The guest names Hecla as a good comparable because its cost of production is very low, and says GoGold aspires to reach those cost levels over time.

Key points on Gogold Resources

  • The CEO says the permitted Los Ricos South build is fully funded from cash — $284 million US at end-June against a $227 million study capex, around $250 million after 8-10% Mexican mining inflation — so no debt is needed.
  • Groundbreaking is set for August with 80% of detailed engineering done, the SAG mill already ordered (a 54-week lead item) and the underground contract awarded, and the CEO says first pour could come ahead of the 24-month study schedule.
  • The company lays out a path from about 2 Moz silver-equivalent a year at Parral (best quarter since 2021) to roughly 9 Moz with Los Ricos South, then 15-17 Moz once Los Ricos North adds another 8.8 Moz, at about $12 all-in sustaining costs.
  • The CEO values the company at over $4 billion at spot commodity prices — Los Ricos South NPV above $1.3 billion, about $2.5 billion for the projects, plus roughly $280 million cash and a Parral NPV over $200 million — against a market cap near $950 million.
  • The district holds 15 years of planned production in reserves plus untested targets — San Pedro/El Nalco about 10 km away and unexplored artisanal ground northeast of the river — while drilling at the North aims to convert a PEA resource (60% indicated, 40% inferred) over the next 6-9 months.

Brad Langille's takeaways

  • Top takeaway Langille argues Los Ricos South is a de-risked, fully funded build: $284 million in cash at end-June versus about $250 million of expected capex, no debt, 80% of detailed engineering complete and long-lead items already ordered.
  • He argues the project can repay its capex about twice over, with the first 18 months underground generating close to half a billion dollars of after-tax free cash flow while Parral keeps producing cash during the build.
  • He lays out an aggressive district timeline: a definitive feasibility study for Los Ricos North in about 9 months and its permit application inputs in about 6, then moving the build team north after first pour to reach 15-17 Moz silver-equivalent a year.
  • He argues the shares are mispriced — more than $4 billion of NPVs and cash at spot versus a market cap near $950 million — and sees a path to 3-4x at lower relative risk than earlier-stage companies.
  • He says Los Ricos is a generational district, expects faster permitting under Mexico's new president, and says the $12 all-in cost margin insulates the company if commodity prices fall.